A cookie is a small text file which a page on Geely Innovation Centre’s website may request to save on your computer. If you do not want cookies to be saved on your computer, you can prevent this by changing the settings on your web browser. If you choose not to accept cookies, you can still use the website but its functionality will be limited.

Geely Innovation Centre’s uses session cookies. These are temporary files which are stored on your computer during the time you visit the website but which are deleted when you close your web browser. Session cookies are used to keep track of which information searches relate to each visitor. The information is not stored nor is it shared with others.

Through Google Analytics, Geely Innovation Centre’s website also uses persistent cookies. These cookies gather information on an aggregated level about how visitors use the website. This may include which pages are shown, the duration of a visit, and which keywords are used. The analysis tool is used to enable us to improve the website on an ongoing basis and to make it easier for visitors to find information. Information which is provided by the cookies is not shared with others and if you do not accept cookies, no information will be gathered.

Important info

There may be shorter periods of suspension of the entrance to Pumpgatan in the beginning of Week 33 during the work of the steel sheet pile. There will be notifications on site. The construction status

  • Week 30. July 26, the crane foundation was made to Crane #1.

  • Pile crane #1. Holding on the pile, there are currently 16 piles left of stage 1. This stage will be completed in week 33.

  • BRA Mark is digging out for future steel cheat pile that started Friday week 32.

  • BRA staff at location : Ingemar Björner, Kent Hartman and Christer Verdin.

  • Our new employees Dennis and Håkan are fixing reinforcement to pump pits.

Upcoming construction work

  • On Monday week 33, the steel sheet pile crane will be established and the crane will start its work in the corner Pumpgatan and Lindholmsallén. This may lead to shorter periods of shutdown of the entrance to Pumpgatan.

  • BRA Mark will in this week start to initiate gross excavation of the pit.

  • Our concrete builders will then begin to cast coarse concrete to ensure that the spont is stuck and that we have a good surface to work on.

  • After this, we will start work on molding the foundation pump and elevator pits.

  • We will now gradually expand the number of our team at site.

  • During week 34, we will assemble our Tower Crane #1.

We understand that the construction work may bring some noises and inconvenience around the area, and we really appreciate your understanding. We will keep you updated regularly on the construction journey.

If you would like to know more or if you have any questions about the project, please visit the official project website at www.geelyinnovationcentre.eu.